*Please note that if you are a current West El & Shawsheen family or staff, we will automatically send updates, no need to sign up!
By the Numbers |
|
---|---|
Enrollment | 1,055 students (includes Pre-K) |
Building Size | 191,028 SF |
MSBA Max Reimbursement Rate | 45.85% |
Effective Reimbursement Rate | 27.41% |
Total Project Budget | $168,066,623 |
Anticipated Maximum MSBA Grant | $46,063,216 |
Anticipated Minimum District Share | $122,003,407 |
January 16 - January 22, 2023 (download)
January 23 - January 30, 2023 (download)
January 31 - February 6, 2023 (download)
February 7 - February 13, 2023 (download)
February 7 - February 13, 2023 (2nd view - download)
February 13 - February 20, 2023 (download)
February 13 - February 20, 2023 (2nd view - download)
February 20 - 27, 2023 (download)
February 20-27, 2023 (2nd view - download)
March 6-13, 2023 (download)
March 6-13, 2023 (2nd view - download)
March 14-20, 2023 (download)
March 27-April 3, 2023 (download)
Overall Steps in the Process
Archived previous presentations (Module 1 - Module 4)
Meetings are live-streamed on Andover TV and may be watched on Comcast 6 and Verizon 43.
To view a previous West El & Shawsheen PreK School Building Committee meeting, click here for video archives. For previous agendas and minutes, click here.
Committee Members | |||
---|---|---|---|
Joel Blumstein | Andrew Flanagan | Lauren Conoscenti | Dr. Magda Parvey |
Janet Nicosia | Keith Taverna Assistant Superintendent of Finance & Administration | Patrick Lawlor | Elizabeth Roos |
Carol Green | Rick Almeida | Mark Johnson | Paul Rollins |
Siggy Pfendler | Armata Kirpalani |
Owner’s Project Manager: PMA Consultants | Architect: SMMA |
Construction Manager: Gilbane Building Company |